Mybase building in Southwark
This live Central London contract involves full cladding remediation, featuring a mix of over 10,000 aluminium panels and Hardie plank, with additional fire proofing works. The built up, busy location of this project has required careful logistical planning with large amounts of materials stored at an industrial unit based several miles away and transported to site as needed. Arrangements are also made for materials stripped from the block to be loaded directly into waiting lorries and taken for recycling.
The project has kept to programme with strong client and consultant relationships supported by an online “weekly progress updates” section within the Breyer website. This features photographs, works updates and safety information for residents and leaseholders living remotely. To ensure the building remains safe while the flammable insulation is removed and cleared from site, we have also installed 72 CCTV cameras to the scaffolding, along with heat detectors, connected to a fire detection system. With additional social value in mind, we hosted a Jobs Fair in Waterloo for the local community to attend.
Key Facts
Contract Name:
Mybase building in Southwark
Client:
My Base 1 RTM Company LTD
Value: £9.5m
Works: Cladding remediation works
Mybase building in Southwark
This live Central London contract involves full cladding remediation, featuring a mix of over 10,000 aluminium panels and Hardie plank, with additional fire proofing works. The built up, busy location of this project has required careful logistical planning with large amounts of materials stored at an industrial unit based several miles away and transported to site as needed. Arrangements are also made for materials stripped from the block to be loaded directly into waiting lorries and taken for recycling.
The project has kept to programme with strong client and consultant relationships supported by an online “weekly progress updates” section within the Breyer website. This features photographs, works updates and safety information for residents and leaseholders living remotely. To ensure the building remains safe while the flammable insulation is removed and cleared from site, we have also installed 72 CCTV cameras to the scaffolding, along with heat detectors, connected to a fire detection system. With additional social value in mind, we hosted a Jobs Fair in Waterloo for the local community to attend.